Management consulting
Investment studies
Project services
Local Service
Performance improvement
Investment banking
Consulting cases
Selected pulp projects
Selected paper projects
Local Service cases
Selected structural projects
Paper
Pulp
Energy
Process industry
Commercial and office buildings
Russian projects
Services > Selected structural projects > Pulp

M-real Oyj, BCTMP plant (HELMI project) Kaskinen Finland

New chemi-mechanical pulping plant, including auxiliary departments, for Kaskinen mill.

The 3D integrated Tekla Structures model was used to check clashes and to ensure compatibility of measures.

Structural engineering objects of refining plant:

  • Storage tower area
  • Flash drying, baling and evaporation plant
  • Bale storage
  • Auxiliary department of electricity, HVAC, control room and office facilities
  • Chip silo, pipe and conveyor bridges foundations
Civil and structural engineering tasks:
  • earthworks and soil reinforcement, pipe bridges, chip conveyor foundations, sewer systems, roads, yards and rail tracks
  • complete prefabricated concrete frame structures
  • storage tower area and drying plants of steel frame structures
  • external walls
Implementation period: March 2004 - August 2005

Andriz, WISA 800 RAC project, Pietarsaari, Finland
New power and chemical recovery line for Pietarsaari pulp mill.

Building volume: 360 000 m3
Building area: 13 600 m2

Project description:
Evaporation plant
Recovery boiler (concrete structures)
Electrostatic precipitator plant
Smoke stack, h=146.5 m
Causticising plant and lime kiln
Turbine plant
Mill office
Raw water pumping station

Mill site planning: earthworks. foundations for pipe bridges, sewerage system, roads, railways and yards

Foundations: soil supported foundations, piled smoke stack foundation

Frame structure: generally prefabricated elements

External walls: sandwich elements, Paroc elements

Duration: May 2002 - March 2004

M-real, Helmi-Project, Finland
Andritz, WISA 800 RAC, Pietarsaari, Finland