Management consulting
Investment studies
Project services
Local Service
Performance improvement
Investment banking
Consulting cases
Selected pulp projects
Selected paper projects
Local Service cases
Selected structural projects
Paper
Pulp
Energy
Process industry
Commercial and office buildings
Russian projects
Services > Selected structural projects > Energy

Fortum Kraftwerk Burghausen GmbH, Wacker Chemie, Gas turbine power plant

Gas turbine power plant with steam boiler

Building volume: 44 000 m3
Building area: 1 100 m2

Preparation of tender documents for the 7 largest subcontracts
Complete civil design

Steel structures:
Construction steel about 1 200 tons
In total about 8 000 steel work shop drawings
Design with the Tekla Structures program.

Cast-in situ concrete:
Foundations, slabs, staircase slip cast,
turbine foundation, machine foundations,
gas station and safety walls for transformers
Other structures: exterior walls, roofs
Erection of steel structure: February - June 2000